Change Management

Overview

Change Management is the third level of ITSM. It handles the approval and planning of changes to the IT system.

Goal: ensure that changes are not made hastily and without a full overview. Specialists from different areas assess risks to avoid follow-up errors. Only Emergency Changes can bypass this process, because the highest priority there is the fastest possible restoration of the system.

Request for Change (RFC)

Before a change is executed, a Request for Change (RFC) is created, typically by Problem Management. The RFC is a formal request to carry out a change. It contains:

  • Description of the change
  • Reason for the change
  • Timeline
  • Priority
  • Expected side effects
  • Estimated costs

The RFC describes what needs to be done, but not how, since the how is worked out in the Change Management process.

RFC Prioritisation

Incoming RFCs are prioritised by urgency and impact:

Urgency Levels

LevelDescription
Priority LowDesirable but not urgent
Priority MiddleNecessary but not urgent
Priority HighImmediate action required
Priority ImmediateImmediate action required

Impact Levels

LevelDescriptionExample
Effect LowMinimal effect on IT services, little effortSwapping one PC
Effect MiddleModerate effect, increased effortUpgrading all PCs' OS
Effect HighHigh effect on IT services, very high effortComplete server outage

Change Types

TypeCharacteristicsApproval
Standard ChangePre-approved routine changes from a catalogue; low risk; automatically authorisedChange Manager alone
Normal ChangeMedium risk, medium complexity, moderate urgency; requires evaluation by expertsCAB + CIO
Emergency Change (Notfall Change)High urgency, short-term solution required; structured approval process is bypassed for speedEC / ECAB

Approval Bodies

BodyDescription
Change Manager (CM)Decides alone on low-reach changes (Standard Change); responsible for time management and monitoring
Change Advisory Board (CAB)Expert committee from various business areas; decides on medium-reach changes (Normal Change)
Chief Information Officer (CIO)Board/management-level person representing IT interests; involved in decisions with large business scope (e.g. staff training)
Emergency Committee (EC / ECAB)Small, highly authorised expert team for urgent decisions; handles Emergency Changes

Change Planning

Forward Schedule of Change (FSC)

A calendar in which all planned long-term changes are documented. Planning should always aim to minimise downtime.

Configuration Management Database (CMDB)

A central database where all CIs are stored with their specifications and licence numbers. All changes to CIs are documented here centrally.

Change Manager (CM) is responsible for time-controlled implementation and monitoring of changes.

Approving and Executing Changes

The separation between approving/authorising and planning/executing a change is intentional in ITSM. This ensures:

  • Sustainable decisions by specialists who consider the overall system
  • Prevention of reactive error fixing without considering the broader context
  • Documented accountability

Closing a Change (PIR)

After a change is implemented, Change Management documents all measures and the root cause for the failure in the CMDB and KEDB for future reference.

The Post Implementation Review (PIR) documents all key points of the change:

  • Test results
  • Implementation details
  • Changes from the previous system state
  • Costs and effort
  • Timestamps

Goal of the PIR: drive continuous improvement by reviewing and evaluating completed changes.

Change Types and Approval Summary

Change typeApproval bodyKey characteristic
Standard ChangeChange ManagerCatalogue-based, pre-approved, low risk
Normal ChangeCAB + CIOMedium risk, CAB involved
Emergency ChangeEC / ECABMaximum speed, structured process bypassed